Cover News Reporter Cao Fei
4月2日,記者從蜀道集團獲悉,隨著第419孔T梁架設到位,隆黃鐵路隆昌至敘永段擴能改造工程專案(以下簡稱“隆黃鐵路隆敘段擴改專案”)架梁進度過半,為專案2025年建成通車奠定了堅實基礎。
Xinglong Township Bridge Paving Site (No. 2 Bridge Erecting Machine)
The Longxu expansion and reconstruction project is an important part of the main railway channel of the western land-sea new corridor, and it is also the main southbound freight channel for the development strategy of "synchronization of the four modernizations, urban-rural integration, and co-prosperity of the five districts" determined by the Second Plenary Session of the 12th Sichuan Provincial Party Committee.
專案全長138.6公里,其中既有線29.2公里,新建線路109.4公里,共需架設T梁836孔,計劃7月完成全線T梁架設工作。
The girder erection conditions of the Longxu section expansion and reconstruction project of the Longhuang Railway are complex, and it has crossed the existing lines, national highways and high-speed rail lines many times. In order to ensure the safe and orderly progress of the paving project, the project team has successively invested 2 beam erection machines in combination with the characteristics of the line, and adopted the "two-machine two-way" collaborative operation mode to efficiently promote the construction progress under the premise of strengthening safety production control.
Mozichong Bridge Paving Site (No. 1 Bridge Erecting Machine)
自2023年12月鋪軌、架梁啟動以來,已架設T梁420孔,鋪軌完成32.3公里,隧道、橋樑、路基工程已進入最後收尾階段,站房、四電等工程有序推進中,預計2025年年底建成通車。
After the completion of the project, it will be connected to the Xuyong-Bijie railway, forming a land-sea intermodal transport artery directly connected to the Beibu Gulf in southern Sichuan, which is not only of great significance for promoting the construction of the Chengdu-Chongqing Economic Circle, but also provides strong transportation support for Sichuan's integration into the national "Belt and Road" construction.
Diagram of Shu Dao Group