6→0 lanes! This highway is "accelerated" and transformed
Updated on: 30-0-0 0:0:0

presently

Jingping Expressway reconstruction and expansion project

More than half of the roadbed and bridge works are progressed

The renovation of the central divider was completed

It is expected to be ready for traffic by the end of this year

The project is located inShunyi District, Pinggu District

It starts from the east bank of the Jingping Chaobai River Bridge in the west

It will be constructed along the existing Jingping Expressway

East to Cui Xing Road Interchange

The total length is about 5.0 km

thereinto

Shunyi District is about 8.0 km

Pinggu District is about 7.0 km

The project adopts the standard reconstruction and expansion of expressways

6 lanes in both directions were widened to 0 lanes in both directions

The design speed remains unchanged at 100 km/h

The width of the roadbed is widened from 5 m to 0.0 m on both sides

A total of 4 interchanges have been reconstructed in the project

involveBlock 2 in Shunyi District

位於北務鎮、大孫各庄鎮

Reconstruction of 6 separate interchanges

involveBlock 5 in Shunyi District

位於北務鎮、大孫各庄鎮

13 bridges were widened

involveDetached interchange of Yangyan Road, Shunyi District

Xuejiazhuang detached interchange and Jewel Tun interchange main line bridge

Xuejiazhuang interchange main line bridge and other 9

1 new interchanges

1 new sub-separation interchanges

At the same time, the construction of greening, environmental protection and other supporting projects

The construction area of the Shunyi section of the Jingping Expressway Reconstruction and Expansion Project.

In the southern part of Shunyi District, the Shunyi section of the Jingping Expressway Reconstruction and Expansion Project, which was constructed by Chengping Jingping Company, pressed the "fast forward button" for construction, setting off a construction boom in an all-round way. On the construction site, more than 300 builders made every effort to speed up the construction progress of key projects such as roadbeds and bridges on the premise of ensuring safety and quality.

Aerial photograph of the Shunyi section of the Jingping Expressway reconstruction and expansion project.

“我們緊抓工序銜接,強化現場安全品質管控,穩步推進施工,目前正在進行路基擋土牆和土方回填施工,預計5月底完成路基土方填築施工作業。”項目負責人陳建峰表示。

Since the implementation of the project, the Shunyi Highway Branch has scientifically and reasonably formulated the construction plan and overcome a number of technical problems. Among them, the connection between the old and new roadbed is a key control project, and the original road surface is occupied for lap treatment during construction, and the traffic section is further reduced, and the construction is difficult. Shunyi Highway Branch and Shoufa Chengping Jingping Company have discussed the construction and guidance plan for many times according to the principle of "ensuring traffic", and finally adjusted it to night construction in a timely manner according to the construction process, set up a traffic diversion team, and carried out traffic diversion throughout the day to minimize the impact of construction on public travel.

After the completion of the project

The expressway network in the northeast of Beijing will be further improved

It is jointly built with Chengping Expressway

It is an express distribution channel that runs through the north and south and connects the east and west

Effectively promote Shunyi District and Pinggu District

High-quality economic and social development

It is convenient for the surrounding citizens to travel

Source: Beijing

Author: Beijing Shunyi official release

[Source: Beijing Daily]