Jingping Expressway reconstruction and expansion project
More than half of the roadbed and bridge works are progressed
The renovation of the central divider was completed
It is expected to be ready for traffic by the end of this year
The project is located inShunyi District, Pinggu District
It starts from the east bank of the Jingping Chaobai River Bridge in the west
It will be constructed along the existing Jingping Expressway
East to Cui Xing Road Interchange
The total length is about 5.0 km
thereinto
Shunyi District is about 8.0 km
Pinggu District is about 7.0 km
The project adopts the standard reconstruction and expansion of expressways
6 lanes in both directions were widened to 0 lanes in both directions
The design speed remains unchanged at 100 km/h
The width of the roadbed is widened from 5 m to 0.0 m on both sides
A total of 4 interchanges have been reconstructed in the project
involveBlock 2 in Shunyi District
位於北務鎮、大孫各庄鎮
Reconstruction of 6 separate interchanges
involveBlock 5 in Shunyi District
位於北務鎮、大孫各庄鎮
13 bridges were widened
involveDetached interchange of Yangyan Road, Shunyi District
Xuejiazhuang detached interchange and Jewel Tun interchange main line bridge
Xuejiazhuang interchange main line bridge and other 9
1 new interchanges
1 new sub-separation interchanges
At the same time, the construction of greening, environmental protection and other supporting projects
The construction area of the Shunyi section of the Jingping Expressway Reconstruction and Expansion Project.
In the southern part of Shunyi District, the Shunyi section of the Jingping Expressway Reconstruction and Expansion Project, which was constructed by Chengping Jingping Company, pressed the "fast forward button" for construction, setting off a construction boom in an all-round way. On the construction site, more than 300 builders made every effort to speed up the construction progress of key projects such as roadbeds and bridges on the premise of ensuring safety and quality.
Aerial photograph of the Shunyi section of the Jingping Expressway reconstruction and expansion project.
“我們緊抓工序銜接,強化現場安全品質管控,穩步推進施工,目前正在進行路基擋土牆和土方回填施工,預計5月底完成路基土方填築施工作業。”項目負責人陳建峰表示。
Since the implementation of the project, the Shunyi Highway Branch has scientifically and reasonably formulated the construction plan and overcome a number of technical problems. Among them, the connection between the old and new roadbed is a key control project, and the original road surface is occupied for lap treatment during construction, and the traffic section is further reduced, and the construction is difficult. Shunyi Highway Branch and Shoufa Chengping Jingping Company have discussed the construction and guidance plan for many times according to the principle of "ensuring traffic", and finally adjusted it to night construction in a timely manner according to the construction process, set up a traffic diversion team, and carried out traffic diversion throughout the day to minimize the impact of construction on public travel.
After the completion of the project
The expressway network in the northeast of Beijing will be further improved
It is jointly built with Chengping Expressway
It is an express distribution channel that runs through the north and south and connects the east and west
Effectively promote Shunyi District and Pinggu District
High-quality economic and social development
It is convenient for the surrounding citizens to travel